AMIETE – ET/CS/IT (NEW SCHEME)      Code: AE62/AC62/AT62

 

Subject: OPERATIONS RESEARCH & ENGINEERING MANAGEMENT

Flowchart: Alternate Process: JUNE 2010Time: 3 Hours                                                                                                     Max. Marks: 100

 

 

NOTE: There are 9 Questions in all.

·      Question 1 is compulsory and carries 20 marks. Answer to Q.1 must be written in the space provided for it in the answer book supplied and nowhere else.

·      Out of the remaining EIGHT Questions, answer any FIVE Questions. Selecting THREE questions from part A and TWO questions from part B.

·      Any required data not explicitly given, may be suitably assumed and stated.

 

 

Q.1       Choose the correct or the best alternative in the following:                                  (210)

                

a.    The feasible solution space of the LP problem represents the area in the ______quadrant in which all the constraints are satisfied simultaneously.

 

                  (A) first                                                (B) second                                                                       

                  (C) third                                               (D) fourth                                                            

 

             b. In the minimization problem, the optimality condition calls for selecting & entering the variable as the ___________ variable with the most positive objective coefficient in the objective function.

       

                  (A) basic                                              (B) non basic

                  (C) primary                                          (D) secondary

 

             c.  ____________ involves the least amount of computations.  

 

                  (A) North west corner method              (B) Least cost method

                  (C) Row minima method                       (D) Vogel’s approximation method

 

             d.  In the PERT networks, pessimistic time ‘b’ which occurs, when execution goes under __________ condition.

 

                  (A) extremely poor                               (B) extremely well

                  (C) normal                                            (D) feasible

 

             e.  The average no. of customer in the system for the queing model system is (where  )

                 

                  (A)                                              (B)                                                                           

                  (C)                                              (D)

            

             f.   The procedure for starting ill behaved Lps with (=) and (≥) constraints is use _____________ variables that play the role of slacks at the first iteration and then dispose of them legitimately at a later iteration.   

                  (A) basic                                              (B) negative

                  (C) artificial                                          (D) non basic

       

             g. ___________________ Management is one of the factors that the engineering manager, especially the newly appointed manager, finds difficult to cope with.

 

                  (A) Administrative                                (B) Production

                  (C) Time                                              (D) Quality

            

             h.  Qualitative forecasting techniques are used when no ___________ data or only unreliable past data are available.

 

(A)  past                                                (B) present

                  (C) correct                                           (D) direct

 

             i.   _________ skill is one of the fundamental requirements of management.

 

                  (A) Managerial                                     (B) Leadership

                  (C) Technical                                        (D) Administrative

 

             j.   Managers concentrate on achieving goals or tasks, which are relatively __________ term targets with a defined beginning and a measurable end result.

 

                  (A) short                                              (B) long                                                                             

                  (C) medium                                          (D) future

 

PART A

Answer any THREE Questions. Each question carries 16 marks.

 

 

  Q.2     a.   Explain with two illustrations to justify the statement or is more than just mathematics.                      (6)

 

             b.   A firm makes two products - X and Y and has a total production capacity of 9 tonnes per day, X and Y requiring the same production capacity. The firm has a permanent contract to supply at least 2 tonnes of X and at least 3 tonnes of Y per day to another company. Each tonne of X requires 20 machine hours production time and each tonne of Y requires 50 machine hours of production time. The daily maximum possible number of machine hours is 360. All the firms output can be sold and the profit made is Rs. 80 per tonne of X and Rs. 120 per tonne of Y. It is required to determine the production schedule for maximum profit and calculate this profit by graphical method.                                           (10)

       

Q.3       a.   Obtain the dual of the following LP problem.                                                        (4)

                    Minimize Z = 3x1 -2x2 + 4x3

                             Subject to Constraints:

                

                        3x1 + 5x2 + 4x3  7

                        6x1 + x2 + 3x3  4

                        7x1 – 2x2 – x3 ≤ 10

                        x1 – 2x2 + 5x3  3

                        4x1 + 7x2 – 2x3  2

                        x1, x2, x3  0

 

             b.   Solve the following LP problem by using (Big – M) method.                             (12)

                   Minimize Z = 2x1 + x2 + 3x3

                   Subject to constraints:

                           x1 + x2 + 2x3 5

                           2x1 + 3x2 + 4x3 = 12

                         and                                                                                                 

 

  Q.4     a.   A wholesale company has three warehouses from which supplies are drawn for four retail customers. The company deals in a single product, the supplies of which at, each Warehouse are:               (8)

                   

         Warehouse no      Supply        Customer no              Demand          

                  

            

                                                    (units)                                             (units)

                        X                             20                   A                              15           

                        Y                             28                   B                              19

                        Z                             17                   C                               13

                                                                              D                               18

                   Conveniently, total supply at the warehouses is equal to total demand from customer. The following total gives the transportation costs per unit shipment from each warehouse to customer.      

Warehouse

Customer

          A                     B                         C                          D

        X

          3

        6

        8

          5

        Y

          6

        1

        2

          5

         Z

          7

        8

        3

          9

 

 

 

 

 

        

 

                   Determine the optimal supplies to despatch from each of the ware houses to each customer so as to minimize the over all transportation cost.

                   Use Vogel’s approximation method to find an initial basic feasible solution.

 

b.     A department has five employees with five Jobs to be performed. The time (in hours) each man will take to perform each Job is given in the effectiveness matrix. 

                        Employees

                                                 I                    II                   III                    IV                  V

       A

      10

     5

     13

      15

      16

Jobs

 
       B

       3

     9

     18

      13

        6

       C

     10

     7

     2

        2

        2

       D

      7

     11

     9

        7

      12

       E

      7

      9

    10

        4

      12

                  

                   How should the Jobs be allocated one per employee so as to minimize the total man hours.                                                                        (8)

            

  Q.5     a.   Define the following terms:                                                                                 (4)

                     (i)   Critical activity                          (ii) Non critical activity

                     (iii) Total float                                  (iv) Free float

                  

             b.  For a small project of 12 activities, the details are given below. Draw the network and find earliest occurrence time, latest occurrence time, critical activities and project completion time.         (12)

                       

                   Activity:            A      B     C      D     E    F    G     H         I         J      K       L

                   Dependence:      _      _     _  (B, C)   (A) (C) (E)   (E)  (D,F,H)  (E)   (I,J)   G

                   Duration:            9     4      7       8       7     5   10      8         6        9      10     2

                    (days)

  Q.6     a.   For the following pay-off matrix, find the value of the game and the strategies of players A and B using linear programming technique.                       (10)

             Player B

            1      2     3

 
 


                                      

 

                                   

             b.   A bank plans to open a single sever drive- in banking facility at a particular centre. It is estimated that 28 customers will arrive each hour on an average.  If on an average it requires 2 minutes to process a customer’s transaction. Determine:                                                                     (6)

                   (i) the proportion of the time that the system will be idle.

                   (ii) on the average how long the customer will have to wait before reaching the      server

                   (iii) The length of the drive way required to accommodate all the arrivals, on the average if 20 feet of drive way is required for each car that is waiting for service.

                                                           

 

PART B

Answer any TWO questions. Each question carries 16 marks.

 

 

  Q.7     a.   Explain the different management tasks that a manager carries out.                      (8)

 

             b.   Explain the need for organizational change. Also briefly explain the many of the barriers a manager faces when change is implemented within an organization.                                                            (8)

                                                                             

  Q.8     a.   Explain the strategy formulation tools and techniques.                                          (8)

 

             b.   Briefly explain the decision making process.                                                        (8)

       

  Q.9     a.   Explain the basic steps employed in the sales process. Also mention the key qualities of sales persons.                                                                   (8)

       

             b.   Explain the techniques and considerations involved in establishing good communications within an organization.                                        (8)